• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar

Reinsurance Focus

New reinsurance-related and arbitration developments from Carlton Fields

  • About
    • Events
  • Articles
    • Treaty Tips
    • Special Focus
    • Market
  • Contact
  • Exclusive Content
    • Blog Staff Picks
    • Cat Risks
    • Regulatory Modernization
    • Webinars
  • Subscribe
You are here: Home / Archives for Arbitration / Court Decisions / Confirmation / Vacation of Arbitration Awards

Confirmation / Vacation of Arbitration Awards

Court Rejects Attempt to Relitigate Arbitration Award

April 2, 2019 by Brendan Gooley

The California Court of Appeal (Fourth District) recently rejected a dissatisfied litigant’s attempt to relitigate an arbitration decision that went against it to the tune of more than $18 million.

An employee of American Claims Management Inc. (ACM), a third-party administrator hired by QBE Insurance Corp. (QBE) to manage QBE’s claims, had a major case of the Mondays and apparently neglected to inform QBE about a demand for a $30,000 policy limit following a car accident. As a result of that “oops,” QBE paid $15 million to settle the claim. QBE then sued ACM for breach of contract. The parties arbitrated the dispute. An arbitration panel awarded QBE nearly $18.5 million.

QBE then petitioned a California trial court to confirm the arbitration award. ACM opposed. The court sided with QBE and confirmed the award, noting ACM appeared to be attempting to relitigate the arbitration award because it did not agree with the panel’s decision. ACM appealed. It raised a number of arguments. Specifically, ACM asserted that the arbitration panel had exceeded its powers by, for example, failing to cite California law, creating law that violated California law, awarding way too much money, and ignoring the Federal Arbitration Act. The appellate court didn’t quite see things ACM’s way, however. It noted that its review was exceptionally narrow and that it could only correct an arbitration award when the arbitrators “exceeded their powers but the award may be corrected without affecting the merits of the decision” (i.e., if the decision was “so utterly irrational that it amounts to an arbitrary remaking of the contract between the parties”). While ACM had couched its arguments in terms of exceeding power, the court concluded that ACM’s “claims amount[ed] to nothing more than assertions of legal error.”

The morals of this case: (1) if you’re a claims administrator, promptly report the claims that come in; and (2) don’t be fooled into thinking that claiming an arbitration panel “exceeded its powers” is a magic password to judicial review.

QBE Ins. Corp. v. Am. Claims Mgmt., Inc., No. D073345 (Cal. Ct. App. Feb. 4, 2019), reh’g denied (Feb. 27, 2019).

Filed Under: Arbitration / Court Decisions, Confirmation / Vacation of Arbitration Awards

D.C. Circuit Court Affirms $1.2 Billion Arbitration Award to Gold-Mining Company

March 15, 2019 by Carlton Fields

Crystallex International Corporation (“Crystallex”) is a Canadian gold-mining company. Crystallex acquired the rights to explore gold deposits in Venezuela through a contract. To explore the mines, Crystallex completed all the permit requirements and posted a bond. The Venezuelan Ministry of Environment denied the permits based on environmental concerns.

Crystallex initiated international arbitration proceedings, alleging that the denial of the permits violated a bilateral treaty between Canada and Venezuela. The arbitration tribunal awarded Crystallex a little more than $1.2 billion in damages. Crystallex petitioned in federal district court for confirmation of the award, and Venezuela opposed and moved to vacate the award under the FAA.

The district court affirmed the award and denied the motion to vacate. Venezuela appealed. On appeal, the court affirmed the district court’s judgment. The court explained that: (1) the district court considered all of Venezuela’s FAA arguments and applied the correct standard of review drawn from FAA case law; (2) the district court did not err in applying a deferential standard to its review of the arbitral award’s method of calculating damages; and (3) the district court did not confirm the arbitral award based on misunderstandings of the arbitration tribunal’s reasoning.

Crystallex Int’l Corp. v. Bolivarian Republic of Venezuela, No. 17-7068, 2019 WL 668270 (D.C. Cir. Feb. 14, 2019)

Filed Under: Arbitration / Court Decisions, Confirmation / Vacation of Arbitration Awards

Eighth Circuit Rejects Claim that Arbitral Award Was Insufficiently Broken Down or Explained

March 7, 2019 by Carlton Fields

Great American denied a claim for coverage for damage to an insured’s corn and soybean crops in three Missouri counties, asserting that the insured had failed “to substantiate an insurable cause of loss” and “fail[ed] to provided adequate records to establish production ‘by unit.'” The insured brought an arbitration seeking coverage, and a three-arbitrator panel awarded him $1.4 million for the damages to his corn crop. Great American moved to vacate the award, arguing that the panel had “imperfectly executed” its powers by failing properly to break down the award “by claim” as required by federal regulations for arbitrations regarding such federally reinsured crop insurance. The district court, finding that the “by claim” requirement meant that an award must break down such claims by county and that the panel had not done this, found this argument sufficient to nullify the entire award.

On appeal, the Eighth Circuit rejected this argument entirely. Recognizing that the regulations require the insurer to determine losses “on a unit basis” and that a unit cannot cover more than one county, the court nonetheless found that a “unit” and a “claim” were not the same thing, and that the arbitrators’ obligation was to break down the award by claim, not by unit. In fact, it was Great American who chose to treat all of these alleged crop losses as one claim, and the panel simply accepted that decision.

Great American also argued that the panel’s explanation for the award amount was insufficient because it merely adopted the calculations of the insured’s expert, but the Eighth Circuit found that this was acceptable, particularly because Great American neither contested this calculation nor offered an alternative calculation. The court thus remanded the case to the trial court so that it could consider Great American’s alternative argument that the panel’s decision rested on an improper interpretation of the applicable regulations.

Great American Insurance Company v. Jonathan L. Russel, No. 17-2441 (8th Cir. Jan. 31, 2019)

Filed Under: Arbitration / Court Decisions, Confirmation / Vacation of Arbitration Awards

Tenth Circuit Affirms District Court’s Confirmation of Arbitration Award While Applying “One of the Narrowest Standards of Review Known to Law”

March 6, 2019 by Carlton Fields

Plaintiffs-Appellants MEMC II, LLC and Mike McDaniel (collectively, “MEMC”) contracted to have Defendant-Appellee Cannon Storage Systems, Inc. (“Cannon”) build a commercial storage facility in Dallas, Texas. The contract included, among other things, precise design specifications and required that any disputes between the parties be resolved by binding arbitration. During construction, Cannon deviated from the agreed-upon design specifications, and MEMC began withholding payments, arguing that Cannon had materially breached the Contract by deviating from those specifications. Cannon continued construction without payment for nearly five months until the parties proceeded to arbitration.

Cannon brought claims for breach of contract based on MEMC’s nonpayment, to which MEMC responded with an affirmative defense, arguing that Cannon’s departure from the design specifications constituted a material breach that discharged MEMC of its payment obligations. Additionally, MEMC counterclaimed for breach of contract due to Cannon’s failure to use the approved plans and specifications. Ultimately, the arbitrator found that MEMC breached the contract by refusing to pay Cannon and that Cannon breached the contract by failing to construct the storage facility according to the agreed-upon specifications. Importantly, the arbitrator did not find Cannon’s breach to be material under Texas law, and therefore, held that MEMC could not evade liability for its refusal to pay.

The District Court for the Western District of Oklahoma confirmed the award and the Tenth Circuit affirmed. The Panel reiterated the narrow scope of judicial review of arbitral awards and found that nothing in the arbitrator’s decision suggested that she did not interpret the contract; in fact, the Panel found the opposite—that the arbitrator considered the respective clauses using relevant case law, weighed the evidence, and decided that, even though Cannon breached the operative contract, its breach did not excuse MEMC from payment obligations. As such, and “[b]ecause the arbitrator interpreted the Contract and applied the law of the jurisdiction selected by the parties, she did not dispense [of] her own brand of industrial justice or exceed her authority under the agreement.”

MEMC II, LLC v. Cannon Storage Sys., Inc., No. 18-6079, 2019 WL 549633 (10th Cir. Feb. 12, 2019).

Filed Under: Arbitration / Court Decisions, Confirmation / Vacation of Arbitration Awards

Ninth Circuit Affirms Order Vacating Arbitration Award, Faults Arbitrator’s Disregard of Contract’s Plain Language

February 26, 2019 by Carlton Fields

The Ninth Circuit recently affirmed a district court order vacating an arbitration award arising from the termination of subcontracts for the construction of army buildings and facilities in Afghanistan. Defendants ECC Centcom Constructors, LLC and ECC International, LLC (together, “ECC”) had two prime contracts with the U.S. Army Corps of Engineers (“USACE”) for the construction of army buildings and facilities in two provinces in Afghanistan. ECC in turn awarded two subcontracts to Aspic Engineering and Construction Company (“Aspic”) for the completion of those projects. Relevant to this dispute, the subcontracts incorporated many Federal Acquisition Regulation (“FAR”) clauses by reference, including those governing termination for convenience, and mandated that Aspic owe to ECC the same obligations that ECC owed to the United States government.

After USACE terminated ECC’s prime contracts for convenience, ECC and Aspic could not agree on a termination settlement amount for both contracts, particularly after USACE refused to pay for any of Aspic’s claimed termination costs. ECC and Aspic proceeded to arbitration to resolve the termination of both subcontracts, and the arbitrator awarded Aspic just over $1 million. Although the award was initially confirmed in California state court, a California federal court later vacated the award, reasoning that it conflicted with contract language. The federal court reasoned that the arbitrator “voided and reconstructed parts of the Subcontracts based on a belief that the Subcontracts did not reflect a ‘true meetings [sic] of the minds.’” Aspic appealed, and the Ninth Circuit framed the issue as “whether the Arbitrator exceeded his powers in finding that Aspic need not comply with the FAR provisions.”

The Ninth Circuit affirmed the district court’s order vacating the award. Specifically, it took issue with the arbitrator’s reasoning that “[t]here was not a true meeting of the minds when the subcontract agreements were entered. Hence, ASPIC was not held to the strict provisions of the subcontract agreements that ECC had to the USACE.” In so finding, the Panel reasoned, “[w]hen an arbitrator disregards the plain text of a contract without legal justification simply to reach a result that he believes is just, we must intervene.” Specifically, it found that the arbitrator’s award in this case was “irrational” because it “directly conflicted with the subcontracts’ FAR-related provisions, without evidence of the parties’ past practices deviating from them, in order to achieve a desired outcome.”

Aspic Eng’g & Constr. Co. v. ECC Centcom Constructors, Case No. No. 17-16510 (9th Cir. Jan. 28, 2019).

Filed Under: Confirmation / Vacation of Arbitration Awards, Week's Best Posts

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 21
  • Page 22
  • Page 23
  • Page 24
  • Page 25
  • Interim pages omitted …
  • Page 115
  • Go to Next Page »

Primary Sidebar

Carlton Fields Logo

A blog focused on reinsurance and arbitration law and practice by the attorneys of Carlton Fields.

Focused Topics

Hot Topics

Read the results of Artemis’ latest survey of reinsurance market professionals concerning the state of the market and their intentions for 2019.

Recent Updates

Market (1/27/2019)
Articles (1/2/2019)

See our advanced search tips.

Subscribe

If you would like to receive updates to Reinsurance Focus® by email, visit our Subscription page.
© 2008–2025 Carlton Fields, P.A. · Carlton Fields practices law in California as Carlton Fields, LLP · Disclaimers and Conditions of Use

Reinsurance Focus® is a registered service mark of Carlton Fields. All Rights Reserved.

Please send comments and questions to the Reinsurance Focus Administrators

Carlton Fields publications should not be construed as legal advice on any specific facts or circumstances. The contents are intended for general information and educational purposes only, and should not be relied on as if it were advice about a particular fact situation. The distribution of this publication is not intended to create, and receipt of it does not constitute, an attorney-client relationship with Carlton Fields. This publication may not be quoted or referred to in any other publication or proceeding without the prior written consent of the firm, to be given or withheld at our discretion. To request reprint permission for any of our publications, please contact us. The views set forth herein are the personal views of the author and do not necessarily reflect those of the firm. This site may contain hypertext links to information created and maintained by other entities. Carlton Fields does not control or guarantee the accuracy or completeness of this outside information, nor is the inclusion of a link to be intended as an endorsement of those outside sites. This site may be considered attorney advertising in some jurisdictions.